You never saw a data center shortage.
Between 2010 and 2018, the number of computing jobs running in the world's data centers rose about 550%, internet traffic rose ten-fold, and storage rose 25-fold. Electricity use rose 6%. Every year a new study predicted the cloud would eat the grid, and every year engineers made servers four times more efficient per computation, moved work into hyperscale buildings that waste a tenth of what a corporate server closet does, and the line stayed flat. Netflix, Zoom, the pandemic, your photos: none of it ran out of room.
Then, around 2019, the line bent. Not because you started streaming more. Because a new kind of server showed up, built around graphics chips that draw ten times the power of the old ones, to train and run AI models. That is the whole story of the chart below: a decade of nothing, then a climb that is real, and then a cliff of forecasts that may or may not be.
"The country is running out of data centers" is false; the internet you use has never had less room than it needed. "AI companies want to build more capacity than has ever existed, ahead of any proven demand for it, and would like you to pay for the grid to reach it" is true. Most of what follows is the gap between those two sentences.
Dig deeper: how a flat line became a cliff
The efficiency decade
The 2020 study in Science that recalibrated the numbers found three things happening at once from 2010 to 2018: processors got far more efficient and wasted less power idling; work consolidated from small, badly cooled company server rooms into hyperscale buildings where the overhead for cooling and power delivery fell to a few percent; and storage moved to drives that use a fraction of the energy per terabyte. Compute rose 550%. Electricity rose 6%. Earlier forecasts, including some that predicted data centers would consume a fifth of world electricity by the 2020s, had simply extrapolated the growth of computing without the efficiency.
What changed in 2019
Training and running large AI models uses graphics processors that draw 700 to 1,200 watts each, packed into racks that draw 100 kilowatts or more where a conventional rack drew 5 to 10. LBNL's 2024 report attributes most of the growth from 2017 to 2023 to this class of server. Its 2025 update puts the 2030 reference case at 649 TWh, 11.8% of U.S. electricity, with a range of 9.5% to 15.3% depending on how many chips ship and how hard they run.
Why the forecasts disagree so much
Two inputs dominate: how many AI chips ship, and how much of the time they run. A shorter assumed chip lifetime cuts LBNL's 2030 estimate to 590 TWh; higher idle power raises it to 782. The IEA, modeling the same country, lands at 426 TWh for 2030. The honest statement is that nobody knows within a factor of two, which matters when utilities are using the high end to justify thirty-year investments.
Global context
Worldwide, data centers used about 415 TWh in 2024, 1.5% of electricity, and the IEA expects about 945 TWh by 2030. The U.S. is 45% of the world total, more than China and Europe combined, which is why the fight over who pays is mostly an American fight.
The number went up six-fold in three years. The country did not.
Every utility files a five-year peak-demand forecast with federal regulators. In 2022 those forecasts added up to 24 gigawatts of growth. In 2025 they added up to 166. Nothing about the physical country changed six-fold in that time. What changed is that developers started shopping the same data center to five utilities at once, utilities started counting every request, and a request became a forecast became a reason to build a power plant.
Dig deeper: phantom load, and why utilities like it
How a request becomes a forecast
A developer with a site option and no tenant files a request for 500 megawatts with the local utility. It files the same request in two other states to see who offers the cheapest power and the biggest tax break. Each utility adds 500 MW to its forecast. The forecast goes into the regional grid operator's plan, which goes into the capacity auction (see §3), which sets the price every household pays. Three "phantom" data centers have now raised your bill before a shovel has moved. Grid Strategies found that utility forecasts collectively overstate data-center-driven growth by about 40% against a proprietary database of real projects.
The incentive
A regulated utility earns a guaranteed return, usually 9 to 11%, on every dollar it invests in plants and wires. More forecast means more investment means more profit. The industry's trade group expects its members to spend $1.1 trillion from 2025 to 2029, nearly matching the previous ten years combined, and is open that data centers are the reason. A forecast that turns out to be too high is not the utility's loss; the plant is built and ratepayers pay for it either way. A forecast that is too low gets a utility blamed for blackouts. The asymmetry points one direction.
What a real forecast looks like
Ohio made AEP require new data centers to pay for 85% of the power they asked for whether they used it or not. The request list fell from 30 GW to 13 GW almost immediately. Texas ordered an audit of every project in its 474 GW queue in August 2026 and then halted new environmental permits for data centers in September until it finishes. Federal regulators ordered every regional grid operator in June 2026 to justify how it handles large-load requests. The pattern in every case: ask developers to put money behind the number, and the number shrinks.
Who the load factor helps
Utilities assume data centers run flat out, 24 hours a day, near 100% of their rated power. Real facilities, even AI ones, average well under that. Grid Strategies flagged that some forecasts use "unrealistically high load factors," which inflates energy forecasts even more than peak forecasts. Every percentage point of assumed utilization is another plant someone gets to build.
The data center isn't built yet. You're already paying for it.
In the grid that serves 67 million people from Chicago to Washington, generators are paid in an annual auction for promising to be available three years out. The price of that promise was $29 per megawatt-day in 2024. It is $333 today, the legal maximum, and the grid's own market monitor says data centers, most of them not yet built, are the reason. That cost lands on every electric bill in thirteen states.
Whether a data center raises your bill depends entirely on rules your state utility commission writes. Ohio, Georgia, Virginia and Texas have started making large loads sign long contracts and pay for their own grid upgrades. Most states have not. The difference is worth billions, and it is decided in hearings almost nobody attends.
Dig deeper: who pays for the wires, state by state
How a capacity market moves your bill
Your utility buys enough "capacity" to cover its share of forecast peak demand plus a reserve. When the forecast jumps because of data center requests, the utility must buy more capacity at auction, supply is fixed in the short run, and the price clears at the cap. The charge is passed through to every customer in proportion to use. A household did nothing different and pays more. The market monitor estimated data centers caused 63% of the 2025/26 price increase ($9.3 billion) and 40% of the 2027/28 cost ($6.5 billion).
The rules that decide who pays
| Where | Rule | What it does |
|---|---|---|
| Ohio (AEP) | Data center tariff, 2025 | Pay for at least 85% of requested power for up to 12 years, used or not; exit fees if a project is canceled. |
| Georgia | PSC rules, 2025 | Loads of 100 MW or more sign custom 15-year contracts and can be billed for upstream generation and transmission, not just the hookup. |
| Virginia (Dominion) | GS-5 rate class, effective 2027 | Loads of 25 MW or more sign 14-year contracts with minimum charges covering 85% of wires costs and 60% of generation, plus upfront collateral. |
| Texas | SB 6, 2025 | Loads of 75 MW or more contribute to interconnection costs and must curtail in emergencies; regional transmission still mostly socialized. |
| Federal (FERC) | Show-cause orders, June 2026 | Every regional grid operator must justify its large-load rules; the Energy Department proposed 100% cost responsibility for upgrades. |
| Oklahoma, New Jersey, Oregon | Ratepayer protection laws, 2025–26 | Separate data center rate classes so that new generation built for them is not spread across households. |
The counter-evidence, honestly
Rutgers' policy lab reviewed residential bills across 24 states in 2026 and found no large, detectable increase attributable to data centers yet; its title was "Mostly Not. Yet." An EPRI study argued that from 2015 to 2024, data centers slightly lowered average rates by spreading fixed costs over more sales. Both are consistent with the PJM story: the costs are front-loaded into capacity and transmission charges that reach bills on a lag, and they are concentrated in the regions building the most. The question is not whether you are paying today but whether the rules will stop you from paying tomorrow.
What else shows up
Gas plants. Entergy will build ten gas-fired units, more than 7 gigawatts, to power Meta's Louisiana campus. Meta pays for the first 15 years; the plants are financed over 30. Consumer advocates asked who pays the second half. In Memphis, xAI ran dozens of gas turbines beside its facility before permits for most of them existed. Water: U.S. data centers consumed about 17 billion gallons directly in 2023 and 211 billion indirectly through the power plants that feed them. Google's Oregon facilities alone used 550 million gallons in 2025, about 40% of The Dalles' total.
Thirty-seven states tax the tire and exempt the chip.
When a carmaker buys a tire, it pays no sales tax, because the customer will pay it on the car. When Amazon buys a $40,000 AI chip for its own data center, 37 states charge no sales tax either, though there is no customer down the line. That one exemption now costs Georgia, Virginia, Texas and Ohio more than a billion dollars a year each. Fourteen states with the same exemption will not say what it costs them. Switch the map to see which states have begun pushing back.
Jobs per billion
Dig deeper: the stadium playbook, the Foxconn precedent, and what the chips are really for
The stadium parallel
Economists have studied publicly funded sports stadiums for forty years and reached one of the strongest consensuses in the field: they do not pay for themselves. In a 2005 survey of American Economic Association members, 85% said state and local governments should stop subsidizing franchises; in a 2017 University of Chicago panel, 80% agreed subsidies cost taxpayers more than they return. Cities build them anyway, because the ribbon-cutting is visible and the cost is spread thin across decades. Data centers are the stadium with the ribbon-cutting removed: a billion-dollar building, a few hundred jobs, a thirty-year tax abatement, and no one in the seats.
Why data centers are a worse deal than stadiums
- The subsidy scales with the hardware, not the jobs. A sales tax exemption on chips grows every time chips are replaced, which in AI facilities is every three to five years. Texas's exemption grew from a $29 million projection to a $1.3 billion cost because of chip purchases nobody modeled.
- Half of the programs don't require a single job. Sixteen of 36 state data center subsidies had no job-creation requirement at all. Of Texas's 138 exempt facilities, 20 have been audited and six of those failed the job rules.
- Local governments lose money they never voted on. A state exemption usually wipes out the local share of sales tax too. Georgia's counties and cities are projected to lose $1.1 billion in 2026 to a break the state legislature granted.
- The subsidy isn't what decides the location. Industry surveys find 3% of operators call incentives the biggest siting factor; power and land are. North Carolina's governor put it plainly in 2026: "The market is already delivering the incentives."
The Foxconn precedent
In 2017 Wisconsin promised about $4 billion in incentives for a Foxconn factory that was to employ 13,000 people in Mount Pleasant. The village and county borrowed hundreds of millions to prepare the site. The factory was never built as promised and employment peaked at about a tenth of the pledge. Microsoft now owns part of the site and is building a data center on it. In September 2026, under its "community-first" pledge, Microsoft waived the $5 million annual incentive the village had offered and redirected it to local tax relief, the first time a Wisconsin economist could recall a company returning one. It is also a measure of how far the ground has shifted: the largest tenant in the industry now advertises that it will pay full property tax and its own grid costs, because communities stopped saying yes.
What the chips are really for
A hyperscale AI building is 55 to 60% chips by cost. Those chips are bought from one company at a 71 to 75% gross margin, depreciate in a few years, and are tax-exempt in 37 states on every replacement cycle. The building that holds them is tax-abated for decades. The electricity that runs them is, in Texas and several other states, also exempt from sales tax. Strip the exemptions out and a 1-gigawatt campus is a $40 to $50 billion purchase of taxable equipment; with them, it is a $40 to $50 billion purchase on which the public collects almost nothing and provides the roads, the water and, through the capacity market, part of the power plant.
The buildout pays the builders. That's the plan.
Four companies will spend about $730 billion on data centers in 2026, nearly double 2025 and five times 2023. Where it goes is not a mystery: more than half to one chipmaker, the rest to construction firms, landowners, power equipment makers, utilities earning a guaranteed return, and the developers and lenders who own the shells. Where it comes from is more interesting: cash flow from ads and software, hundreds of billions in new debt, and a loop in which the chipmaker invests in its customers so they can buy its chips.
Where it comes from
- Ad and software profits from Google, Meta, Microsoft and Amazon, the only companies that can fund this from cash
- Debt: Oracle carries more than $100 billion and has negative free cash flow; private credit funds and bond markets supply the rest
- Public money: sales tax exemptions, property abatements, grid upgrades paid through everyone's bill, water at municipal rates
- The loop: Nvidia invests in OpenAI, OpenAI signs a $300 billion cloud contract with Oracle, Oracle borrows to buy Nvidia chips
The buildout
- $35–55 billion per gigawatt of AI capacity, all in
- 55–60% chips, replaced every 3 to 5 years
- 30–35% building, power and cooling, $10 to $25 million per megawatt before any chip arrives
- 7,481 MW under construction in North America in mid-2026, a record, 80% pre-leased
Who collects
- Nvidia: $216 billion in fiscal 2026 at a 71% margin
- Utilities: $1.1 trillion of rate-based investment through 2029 at a 9 to 11% guaranteed return
- Developers and REITs: shells leased for 15 to 20 years; Riot's single Anthropic lease is worth $9.1 billion
- Construction, land, turbines, transformers: a 7,500-worker peak at one Louisiana site
- Not on the list: the county, after the construction crews leave
The loop, step by step
Dig deeper: utilities, REITs and the private-credit layer
The utility business model, in one paragraph
An investor-owned utility does not make money selling electricity; it makes money owning things. Regulators let it earn an allowed return, typically 9.5 to 10.5%, on the capital it has invested in plants and wires, recovered through rates. Growth in that "rate base" is the whole earnings story. NiSource targets 9 to 11% rate base growth a year through 2033 and credits data centers. Sempra plans a record $65 billion through 2030, mostly in Texas, and expects its rate base to nearly double. The trade association expects $240 billion of utility capital spending in 2026 alone. Every one of those dollars earns a return from ratepayers whether the data center that justified it ever draws power.
Who owns the buildings
Most hyperscale capacity is leased, not owned, by the tech companies. The landlords are data center REITs (Equinix, Digital Realty), private equity-backed developers (QTS under Blackstone, Vantage, Crusoe, Aligned) and, increasingly, former bitcoin miners who already had power contracts. The leases run 15 to 20 years with investment-grade tenants, which makes the buildings easy to finance with debt. If the tenant's AI business does not materialize, the lease is still owed; if the tenant walks, the building is a very expensive shed in a county that gave up its property tax to get it.
The cancellations
Microsoft was reported to have walked away from leases totaling a couple of gigawatts in early 2025, which analysts read as oversupply against its own demand forecast. Oracle and OpenAI dropped the Abilene expansion in March 2026. Industry trackers put the share of U.S. 2026 capacity that has been delayed or canceled somewhere between a third and half, though the figures mix opposition, permitting, financing and power delays. None of this has slowed guidance: every hyperscaler raised its 2026 spending plan at least once during the year, and the stated reason is often not demand but the rising price of memory chips.
The jobs number, honestly
Construction employment is real and large: 7,500 at the peak of Meta's Louisiana build, thousands at Abilene, enough to cause a housing crisis in a city of 130,000. It is also temporary and largely imported. The permanent payroll of a hyperscale campus is a few hundred technicians and security staff. A typical measure of what the public gets per dollar, permanent jobs per billion invested, runs from 4 to 50 for data centers against roughly 1,000 for an auto plant.
The playbook was written by bitcoin miners.
Before AI, the industry that taught developers how to get a municipality to pay for a building full of chips was bitcoin mining. The model: find cheap power and a county that wants investment, get the state's data center tax exemption (most do not exclude crypto), sign up for grid programs that pay you to switch off, run the machines when power is cheap, and sell the whole thing as a "data center" when the AI money arrives. In one month in 2023 the largest U.S. miner made three and a half times more from not mining than from mining.
Dig deeper: the mining-to-AI pipeline and why it works
The asset was never the bitcoin
A bitcoin mine is a power contract with computers attached. Miners went where power was cheapest and least regulated, mostly Texas, signed long fixed-price contracts with generators, and enrolled in the grid's demand-response programs, which pay large customers to drop load when the grid is stressed. In a heat wave, a miner earns more by selling its contracted power back to the grid than by mining. Senators Warren and Markey called the payments subsidies; the industry calls its load a "demand-side battery." Both are describing the same transfer: from everyone's bill to a company that agreed to turn off something it only turned on because the power was cheap.
The tax break came free
Most state data center sales tax exemptions were written before anyone imagined a building full of ASICs, and most do not exclude crypto mining. A miner in a qualifying state buys its machines and often its electricity tax-free, like any other "data center." Good Jobs First's first recommendation for any state that keeps its exemption is to disqualify crypto facilities from it.
The pivot
When the AI boom arrived, miners discovered their power contracts and interconnections were the scarcest asset in the industry. Core Scientific, TeraWulf, Cipher, IREN and Riot converted mining halls into GPU hosting and signed leases with AI companies that dwarf their old revenue. Riot's first tenant was AMD at 50 MW; its second was a 20-year, 191 MW lease with Anthropic worth about $9.1 billion through 2048. The county that approved a bitcoin mine with a tax abatement now hosts an AI campus with the same abatement, and the municipality that paid to upgrade a substation for a business that could switch off at any time now serves one that cannot.
The noise
Mining and AI facilities both run tens of thousands of fans. Residents of Granbury, Texas recorded about 85 decibels, the level of a running blender, from Marathon's 300 MW mine beside a gas plant, and reported migraines, vertigo and hearing damage. A court allowed their suit to proceed in 2025. Texas does not allow counties or its environmental agency to regulate noise, which is one reason the mine is in Texas.
Your chatbot costs almost nothing. The buildout is not for your chatbot.
A text prompt uses about as much electricity as nine seconds of television. An image, roughly a phone charge's worth at most. A short AI video is the expensive one. Add up a heavy day of all three and you get less than the energy to make one cup of coffee. That is the honest number, and it is also why the energy argument about AI is usually made badly in both directions: your use is trivial, and the buildout is enormous, and both are true because the buildout is not sized to what people use. It is sized to what companies hope to sell, and to training runs that now draw as much power as a small city.
Google cut the energy of a prompt by 33 times and its electricity bill rose 37% in the same year. Efficiency does not reduce the buildout; it lowers the price of a prompt until there are more prompts, more models, more video, and more buildings. The buildings are not a response to your demand. They are a bet that making AI cheap enough will create it.
Dig deeper: training vs. using, idle chips, and what "need" means
Two different loads
Inference, answering your prompts, is small per task and large in aggregate only at planetary scale. Even a heavy user's day is under a tenth of a kilowatt-hour. If every American ran the calculator's "typical" day, the country's AI use would be roughly 7% of what data centers already consume. Training is the opposite: a handful of runs a year, each drawing 100 megawatts or more continuously for months, with the next generation planned at a gigawatt or more. Training is what the gigawatt campuses in Texas, Louisiana, Georgia and Indiana are for, and it is a bet on models that do not exist yet.
Built ahead of demand
The chips are bought before the customers are. Microsoft said in late 2025 that it had chips in inventory it could not plug in because buildings and power were not ready; Oracle built the Abilene campus for one customer whose revenue cannot yet cover the contract; Meta's Louisiana campus is being sized to 5 gigawatts for products nobody has used. None of that is a shortage in the sense a household experiences one. It is capacity purchased on the expectation that demand will arrive, financed partly by the public, with the downside held by ratepayers and counties if it does not.
What the per-task numbers hide
Published per-prompt figures are mostly for text and for a company's own median; a long reasoning answer can use ten to fifty times the median. Video generation is the category to watch: measurements span a 3,000-to-1 range depending on the model and settings, and the expensive end is the one being marketed. Image and video are also where the "generated imagery" demand is growing fastest. The fair summary: text is nearly free, images are cheap, video is not, and the aggregate depends on how much of it companies can convince people to make.
What would "need" look like?
A build that followed demand would show chips running near capacity before the next campus is announced, forecasts that match shipments, and tenants paying for their own power. What the record shows instead is utilization nobody publishes, forecasts 40% above shipments, canceled expansions, and the public asked to underwrite the gap. Whether the bet pays off is a question for investors. Who holds the downside is a question for voters.
The only thing that has worked is saying no.
In the first three months of 2026, local opponents blocked or delayed 75 data center projects worth $130 billion, the most since anyone started counting. New York imposed the first statewide moratorium in July. Texas, the industry's favorite state, froze permits in September pending an audit. California passed a seven-bill package the same week. The issue has crossed every party line there is: 14% of Americans say they would welcome a data center in their community, and candidates in both parties have noticed.
What a county or city can demand
- No property tax abatementMicrosoft now pledges to pay full tax everywhere; others will when asked
- Pay for your own gridA large-load tariff with a minimum bill, like Ohio's 85% rule, so phantom requests cost the requester
- No non-disclosure agreementsPennsylvania banned them by executive order in August 2026; most "Project Blue" deals depend on them
- Water and power disclosure, annuallyTucson learned its project's water use from an advocacy group's records request
- Clawbacks tied to permanent jobsSix of twenty audited Texas facilities missed their job requirements
- Bring your own powerMaryland's bill would allow data centers only if co-located with new generation
- A pause while you countGood Jobs First's own recommendation: a moratorium long enough to learn the costs
What the pitch will tell you
- "Thousands of jobs"Construction jobs, for two years, mostly from out of town
- "Millions in new tax revenue"Net of the abatement that is the condition of the deal
- "They'll build it somewhere else"Power and land decide siting; 3% of operators say incentives do
- "It will lower everyone's rates by spreading costs"True in 2015, when data centers were small; the capacity market says otherwise now
- "The water is recycled"Direct use is modest; the power plant that feeds it is where most of the water goes
- "If we don't build, we lose the AI race"The race is between four companies, and your county is not in it
Dig deeper: what states did in 2026
| When | Where | What |
|---|---|---|
| Jan 13 | Microsoft | "Community-First" pledge: pay full property taxes, pay rates that cover new generation and grid upgrades, no NDAs with local governments |
| Apr–May | Florida, Oklahoma | Hyperscale Data Center Act (Fla.) and Data Center Consumer Ratepayer Protection Act (Okla.) create separate rate classes so households don't fund new plants |
| May | Ohio | Governor pauses the sales tax exemption for new applicants after the $1.6 billion cost is revealed |
| Jun 4 / Jul 14 | New York | Legislature passes a moratorium bill; governor instead signs an executive order pausing new 50 MW+ facilities for up to a year |
| Jun 18 | FERC | Show-cause orders to all six regional grid operators on large-load interconnection rules |
| Aug 3 / Sep 21 | Texas | Governor orders an audit of 474 GW of requests, then halts new environmental permits for data centers until it is done |
| Aug 18 | Pennsylvania | Executive order bars non-disclosure agreements with data center developers |
| Sep 8 | Massachusetts | Executive order imposing statewide restrictions |
| Sep 21 | California | Governor signs a seven-bill data center package, the most comprehensive state law |
| Sep 28–29 | Microsoft / Mount Pleasant | Microsoft waives a $5 million annual incentive at the former Foxconn site; the village applies it to property tax relief |
| Nov 3 | Ohio, Florida, others | Local ballot measures on data center moratoriums and bans; data centers a declared issue in dozens of congressional and gubernatorial races |
Not every "restriction" restricts. Several of the 2026 state laws are ratepayer-protection measures that make the buildout easier to approve by moving its cost off households, which is the industry's preferred outcome. The projects that actually stopped were stopped by zoning boards, county commissions and city councils, usually over water, noise, farmland or an abatement, and usually after residents found out what the NDA was hiding.
Who wins, who pays, who decides.
The same ledger, as plainly as the data allows.
AI uses real electricity and some of the buildout is needed. But "needed" has been stretched to cover forecasts inflated by 40%, subsidies that scale with hardware instead of jobs, grid costs socialized onto households, and a financing loop in which the seller funds the buyer. Nobody has to decide whether AI is good to decide that the people building its warehouses should pay for their own power, their own taxes and their own water. That is the only question on your local ballot, and it is the only one that has ever changed the outcome.